Nexus Insight

Control Tower

One screen linking PoC evidence, operational KPIs, approval gates and budget. Every metric has an accountable owner and a next action.

Current gate: G2 — Platform SelectionData refreshed 17 Aug 2026 09:15

Platform assessment score

63.4

100-point framework · critical gaps left: 1

Critical scenarios passed

81/97

6/10 PoCs complete · 83.5% pass rate

Pilot budget spent

730 M ₫

Hard cap 1.50 B ₫ · 770 M ₫ remaining

Customisation index

22

Lower is closer to fit-to-standard; the alert threshold is 45

Gate Review G0 → G4

Evidence → Gap → Cost → Risk → Decision. Budget opens only when a gate is approved.

G0

Baseline

Day 0–30

4/4 criteria · Approved

G1

Blueprint

Day 31–60

5/5 criteria · Approved

G2

Platform Selection

Day 61–90

4/5 criteria · In review

G3

Wave Rollout

Month 4–9

0/3 criteria · Not open

G4

Value Realization

Month 10–12

0/3 criteria · Not open

Key KPIs

Each KPI has an owner and a next action. Metrics off target are flagged for the current sprint.

  • Time-to-PoC

    On target

    Product Lead · Hold the pace with a reusable library of PoC scripts

    24days

    target 30

  • Critical test pass rate

    On target

    QA/UAT Lead · Close the 4 remaining scenarios in P6 and P7

    96.40%

    target 95

  • Integration message success

    On target

    Integration Engineer · Keep the DLQ under 20 messages a day with backoff retries

    99.93%

    target 99.9

  • Barcode scan accuracy

    On target

    BA Inventory · Replace 6 ageing scanners in the raw-material warehouse

    99.62%

    target 99.5

  • Month-end close

    Off target

    BA Finance · Automate the 4 reconciliation steps still done by hand

    5.50days

    target 5

  • Average OEE

    Off target

    Enterprise Architect · Cut changeover downtime on production line 2

    71.40%

    target 75

Blocking G2

Waiting on the last 4 critical scenarios in P6, P7 and P10

100% of critical scenarios pass

93 of 97 scenarios pass, 4 still running

Open PoC Lab to close the remaining scenarios

Sprint 2 — Assessment Engine

The 100-point framework runs and the fit-gap matrix can be exported

Story point progress36/38

33

avg velocity

28 Sep 2026

ends

G1

gate at sprint end

View the sprint board and risk register

Status of the 10 mandatory PoCs

A PoC only counts as passed when every critical scenario passes on real data.

  • P1

    E2E Purchase-to-Pay

    PR → PO → Goods receipt → Invoice → Payment

    12/12Passed
  • P2

    MRP / APS

    Demand → Materials → Production schedule

    9/9Passed
  • P3

    MES / OEE

    Production order → Machine data → OEE

    6/10Running
  • P4

    BOM / Routing / Costing

    BOM → WIP → Actual cost → Variance

    11/11Passed
  • P5

    Barcode & Traceability

    Receipt/Issue → Barcode → Lot traceability

    8/8Passed
  • P6

    QMS

    IQC/IPQC/OQC → NCR/CAPA → Release

    5/9Running
  • P7

    EAM / CMMS

    Asset → PM → Work order → Spare parts → MTBF/MTTR

    4/8Running
  • P8

    Intercompany & Finance

    Internal buy/sell → Payables → Costing → Reconciliation

    10/10Passed
  • P9

    BI / Control Tower

    KPI → Alert → Drill-down → Owner → Action

    9/9Passed
  • P10

    OT / API Integration

    External device or system → Integration → Message success

    7/11Running

Risks to watch

Ranked by probability × impact; each risk has a control and an owner.

  • The company is perceived as a consultancy rather than a software product

    20

    Clear IP ownership, subscription revenue, a code repository and a public product roadmap

    Owner: Founder

  • Excessive customisation inflates TCO and upgrade risk

    20

    Fit-to-standard principle, change control and a customisation index

    Owner: Enterprise Architect

  • Poor customer data quality makes the PoC inconclusive

    20

    A mandatory data readiness gate before G1 with a minimum score of 80

    Owner: Data/AI Engineer

  • Dynamics 365 licence cost exceeds what an SME can afford

    16

    Start with Business Central, use startup benefits, expand in stages

    Owner: Product Lead

Budget discipline

No spend beyond a gate. Every customisation is converted into TCO and risk before approval.

G0

250 M ₫

budget released

G1

480 M ₫

budget released

G2

Waiting

rollout budget not open

Pilot cap

1.50 B ₫

locked at G0